2023 Chip Seal Plan
Chip sealing and fog sealing are extremely dependent on weather, equipment, supplies and staffing. The plan below lists roads in roughly the order they will be chip sealed, but exact dates or weeks are not predictable until the season starts.
Planned dates for roads may be added as the season progresses but are subject to change. Dates completed will be added as paperwork from the field is processed.
Watch this page for updates on the season's progress if you are interested in when we will reach a particular road or neighborhood. However, the electronic message boards we post on main roads are our primary method of notifying you that work is going to begin in each area of the county.
Road Name |
Last surface date |
Start milepost |
End milepost |
Chip-seal date |
Fog-seal date |
---|---|---|---|---|---|
Old Fort Townsend Rd |
1999 | 0.00 | 0.53 | ||
Glen Cove Rd |
1995 | 0.00 | 0.23 | ||
Mill Rd |
2011 | 0.03 | 0.77 | ||
Gibbs Lake Rd |
2005 | 0.00 | 0.942 | ||
Country Ridge Dr |
2001 | 0.00 | 0.28 | ||
Blue Mountain Rd |
2001 | 0.00 | 0.51 | ||
W Egg & I Rd |
2000 | 0.00 | 0.44 | ||
Egg & I Rd |
2000 | 0.00 | 0.73 | ||
West Valley Rd |
2002 | 2.30 | 5.56 | ||
Anderson St |
2003 | 0.00 | 0.12 | ||
10th Ave |
2003 | 0.00 | 0.13 | ||
W Eugene St |
2003 | 0.00 | 0.12 | ||
9th Ave |
2003 | 0.00 | 0.05 | ||
W Melissa St |
2007 | 0.00 | 0.12 | ||
W Swaney St |
2001 | 0.00 | 0.33 | ||
W Maude St |
2001 | 0.00 | 0.31 | ||
W Kincaid St |
1986 | 0.00 | 0.29 | ||
9th Ave |
2001 | 0.00 |
0.29 | ||
8th Ave |
2009+ | 0.03 |
0.22 | ||
W Price St |
2003/2022 | 0.00 | 0.114 | ||
7th Ave |
2012+ | 0.00 | 0.41 | ||
Thousand Trails Rd |
2005 | 0.00 | 0.98 | ||
Zelatched Point Rd |
2005 |
0.00 |
1.04 | ||
Hazel Point Rd |
2005 | 0.00 | 1.05 | ||
Whitney Rd |
2005 | 0.00 | 0.10 | ||
E Go-Onna Dr |
2005 | 0.00 | 0.48 | ||
W Go-Onna Dr |
2005 | 0.00 | 0.12 | ||
Coyle Rd |
2004 | 0.00 | 14.64 | ||
Camp Harmony Rd |
1988 | 0.00 | 0.02 |