- Home
- Government
- Departments F-Z
- Public Works
- Port Hadlock Wastewater System
Port Hadlock Wastewater System
Jefferson County, WA is developing a sewer system for the Irondale & Port Hadlock Urban Growth Area (UGA) to provide wastewater treatment for local residents and businesses. The sewer system has been identified as a critical element for increased regional economic development. When construction of the sewer system is completed, the Irondale & Port Hadlock UGA will be able to support affordable housing, medical facilities, higher density multifamily residences, senior housing, as well as commercial and industrial development.
Below are some items from the March 2023 newsletter, which provides an update on the progress of the Port Hadlock Wastewater System Phase I project.
Phase I Service Area
The map shows the proposed Phase I sewer system boundary outlined in green. The treatment plant and percolation pond are shown in orange, the inlet line to the wastewater plant is shown in yellow, and the proposed pressure sewer collection lines are a magenta color.
Bidding of First Phase of Construction
Bids for the first phase of construction for the project are due March 30, 2023. This phase includes: site work and grading, construction of the inlet pipe from State Highway 116 to the treatment plant site, effluent pipe from the treatment plant site to the percolation pond, percolation pond, mitigation plantings, and various other utility installations like water, power, and fiber optics.
Project Schedule
Following is the anticipated project schedule, which is subject to change.
Estimated Date | Component | Comments |
March 2023 – October 2023 | Bid and start on construction of Treatment Plant |
|
October 2023 – December 2023 | Bid and start construction on specifically defined areas of the Pressure Sewer |
|
July 2024 – July 2025 | Property Connections |
|
May 2023 – December 2023 | Sewer Ordinance |
|
Fall 2025 | Wastewater System Operational |
|
Project Cost and Funding (numbers rounded) – Our existing project cost estimate for construction totals $34 million. The Table below summarizes Phase I funding for construction and currently indicates that funding is adequate to complete the Phase I project:
Amount | Status | Source | Purpose |
$3.4 Million | Secured | County – American Rescue Plan Act | Administrative, County management staffing, matching funds for certain grants |
$20 Million | Secured | State – Rep. Tharinger and Legislative Appropriation | Construction – Wastewater treatment plant, inlet line, percolation pond, and some portion of pressure sewer system |
$2.5 Million | Secured | Federal – Senator Murray Appropriation | Construction – Pressure Sewer and Grinder Pumps |
$3.0 Million | Secured | Federal – Rep. Kilmer and Senator Cantwell | Construction - Pressure Sewer and Grinder Pumps |
$6.7 Million | ECY Recommended, requires WA State Legislature final approval | State Dept. of Ecology Grant | Construction – Pressure Sewer and Grinder Pumps |
$35.6 Million | Total Funding Package for Phase I Wastewater System Construction |
Phase 1 Sewer Service Area Map (June 2022) with Zoning
The area indicated within the green lines on this map is the Phase 1 service area. The map also shows what the zoning will become when the PHUGA sewer system is operational.
State allocates $20.175 million for Port Hadlock Sewer project
The State Legislature allocated $20.175 million in 2021 for construction of the Port Hadlock Sewer. The project funding is derived from recent federal relief and infrastructure packages received by Washington State and comes just weeks after the Department of Ecology approved the Sewer Facility Plan for the project. Both The Leader and Peninsula Daily News reported the news in the Wednesday, 4/28/2021 editions of their papers.